In January 2023, New Zealand’s Coromandel region was hit by severe weather causing a 115m long and 20m deep underslip on SH25A. We worked on a solution with NZTA and partners, enabling the highway to open six months after design commenced.
In January 2023 New Zealand’s Coromandel Peninsula experienced a 1-in-200-year storm. 300mm of rain fell in 60 hours, causing a large underslip on State Highway 25A (SH25A).
Reopening the road required a three-span bridge to be designed and built. Beca (Bridge Engineer), Tonkin+Taylor (Geotechnical) and McConnell Dowell and Fulton Hogan (Constructor in a joint venture) formed a team that drove an unprecedented level of collaboration with NZTA Waka Kotahi, local supply chain and community.
A project this scale usually takes up to two years, particularly given the challenging physical location, variable geotechnical conditions and limited contractor capacity.
Clear and delivery-focused client objectives enabled creative and efficient decision making, further reducing delays. The use of off-site construction, utilising available materials, executing design and construction in parallel, and incorporating innovations developed for other similar projects kept the project on track.
The team delivered a new 100-year design-life bridge in six months, representing an industry step-change in collaboration and project delivery. The accelerated design and build programme finished three months early, under budget, and just in time for Coromandel businesses to welcome visitors for the holiday season.
Awards
-
New Civil Engineer Bridges Awards - Bridge Project Team of the Year
-
2024 Āpōpō Awards - Innovation Award
124m
Bridge across the slip
6 months
Delivery timeframe
3 months
Ahead of schedule
What We've Done
Our People
Nathan McKenzie
Principal / Technical Director - Geotechnical